Difference between revisions of "Foo"

From Fixme.ch
Jump to: navigation, search
(Schedule)
 
(62 intermediate revisions by 5 users not shown)
Line 1: Line 1:
= Name =
+
[[Category:Closed_Projects]]
Internal Server
+
 
== Description ==
 
== Description ==
The HS need to be tidy in his IT, centralized everything
+
* The HS need to be tidy in his IT, centralized everything
== Goal ==
+
* Service currently running on the server: [[:Category:Services|List of services]]
Provide a server internal to the hackerspace.
+
 
== Obstacle ==
+
 
== Requirements ==
 
== Requirements ==
The services that would be nice to have are listed below.  
+
The services that would be nice to have are listed below.
 +
* other ideas : http://hackerspaces.org/wiki/Hackerspace_Software
  
Services available only from inside the HS
+
=== Services to come ===
* MPD Daemon
+
* Join SpaceNET for authentication ? https://spacefed.net/wiki/index.php/Spacenet
* ssh key updater (put the key on a single machine which then upload the key on guest1, guest2)
+
* WAITING ON LDAP IP over DNS server (http://thomer.com/howtos/nstx.html, http://code.kryo.se/iodine/ seems better as it support authentication)
* OpenLDAP Server for personal identification (wifi and login into guest1 and guest2, wiki, ftp)
+
* WAITING ON LDAP SSH or openvpn to access the hackerspace for ctf or other event
* Sync guest1 and guest2 to be the same and to share all the software installed
+
* MAYBE ONE DAY bug tracker
 +
* [http://wiki.hamburg.ccc.de/ChaosVPN::Howto ChaosVPN]
  
Services available from anywhere
+
== Received Money ==
* FTPServer on ssl or ssh
+
* [[User:Speredenn|Speredenn]] : 20.- CHF
* git server (gitolite ?)
+
* [[User:FreeStorm|FreeStorm]] : 100.- CHF
 
+
* [[User:Gcmalloc|Gcmalloc]]  : 124.- CHF
The internal requirement for the server:
+
* less than 40 Watt on load
+
* RAID for fallback
+
* easy backup
+
* encryption of some directory would be nice to have
+
  
 +
'''We need 67.60 CHF to end this project.'''
  
 
== Schedule ==
 
== Schedule ==
 
The goal is to have it before the beginning of january 2012
 
The goal is to have it before the beginning of january 2012
== Participant ==
+
* 09 november 2011 : we made some benchmark on a atom N270, with heavy load on an apache server, sshd daemon, mpd and vsftp. Everything is working flawlessly :) so we can go for the dual core atom. The ftp connexion were around 15 MByte per connexion. We need at least 8 Go of ram for that.
Rorist, gcmalloc, Speredenn
+
* 01 december 2011 : The motherboard JNF81-T56N was ordered,should be there 6 days later.
 +
* 02 december 2011 : The motherboard JNF81-T56N is out of stock, need to wait.
 +
* 13 December 2011 : The server is up and running. Waiting for it to be network configured and to filter the services.
 +
* 04 January 2012 : The server is up and running, multiple services will follow in their own project.
 +
* 20 January 2012 : The server is racked.
 +
* 18 July 2020: The server has been serviced, fan oiled and everything cleaned
 +
 
 +
== Project Leader ==
 +
* [[User:Gcmalloc|Gcmalloc]]
 +
 
 +
== Participants ==
 +
* [[User:Rorist|Rorist]]
 +
* [[User:Speredenn|Speredenn]]
 +
* [[User:FreeStorm|FreeStorm]]
 +
* [[User:Francois|Francois]]
 +
* [[User:Nemen|Nemen]]

Latest revision as of 22:19, 18 July 2020

Description

  • The HS need to be tidy in his IT, centralized everything
  • Service currently running on the server: List of services

Requirements

The services that would be nice to have are listed below.

Services to come

Received Money

We need 67.60 CHF to end this project.

Schedule

The goal is to have it before the beginning of january 2012

  • 09 november 2011 : we made some benchmark on a atom N270, with heavy load on an apache server, sshd daemon, mpd and vsftp. Everything is working flawlessly :) so we can go for the dual core atom. The ftp connexion were around 15 MByte per connexion. We need at least 8 Go of ram for that.
  • 01 december 2011 : The motherboard JNF81-T56N was ordered,should be there 6 days later.
  • 02 december 2011 : The motherboard JNF81-T56N is out of stock, need to wait.
  • 13 December 2011 : The server is up and running. Waiting for it to be network configured and to filter the services.
  • 04 January 2012 : The server is up and running, multiple services will follow in their own project.
  • 20 January 2012 : The server is racked.
  • 18 July 2020: The server has been serviced, fan oiled and everything cleaned

Project Leader

Participants