The goal is to have it before the beginning of january 2012
* 09 november 2011 : we made some benchmark on a atom N270, with heavy load on an apache server, sshd daemon, mpd and vsftp. Everything is working flawlessly :) so we can go for the dual core atom. The ftp connexion were around 15 MByte per connexion. We need at least 8 Go of ram for that.
* 01 december 2011 : The motherboard JNF81-T56N was ordered, should be there 6 days later.* 02 december 2011 : The motherboard JNF81-T56N is out of stock, need to wait 
== Project Owner ==
* gcmalloc